Select Page



Basinwide Supplementation Evaluation Project: 2013 Annual Progress Report

Jun 28, 2021

Abstract

This report summarizes activities for the period May 1, 2013 to December 31, 2013, as part of the multi-year project organized under the seven project objectives. The primary focus of the Project involves Hatchery RM&E – specifically molecular genetic studies financed through the Project to assess critical uncertainties related to effects of hatchery supplementation on productivity of depressed natural salmon populations, as well as of stocks that have been reintroduced following extirpation of the native populations.

Authors

Citation

Galbreath, P.F., M.A. Hess, A.P. Matala, and S.R. Narum. 2014. Basinwide supplementation evaluation project: 2013 annual progress report. Columbia River Inter-Tribal Fish Commission Technical Report 14-11, for U.S. Bonneville Power Administration Project 2009-009-00. Portland, OR. 21p.

Date

2014/01/01

Report No.

14-11

Media Type

CRITFC Technical Report